Project
Description
S.R. 0081, Section 005
|
|
|
|
|
 |
|
S.R. 0081 Section 005
Dauphin
County
Construction inspection and documentation services for reconstruction
of all
six lanes of mainline roadway pavement and
shoulders; some interchange ramp improvements; structure improvements
including reconstruction of bridge decks, some of which are also being
widened; updated signing including the installation of several new
overhead variable message signs (VMS); new drainage; and new guiderail
in Susquehanna and Lower Paxton Townships.
|
More Project
Construction Photos

|
|
Client: PENNDOT
District 8-0
Harrisburg, PA
|
| Project Cost: $74.0 M |
| Completion Date: 2004 |
| Complete rehabilitation of
highway involving new construction, reconstruction and shoulder restoration
work. Roadway will be constructed of plain cement concrete pavement,
RPS on treated permeable base over subbase with plain cement concrete
pavement for the shoulders. Thirteen bridge structures, bituminous
paving material for widening and resurfacing existing roadways, drainage,
concrete glare screens and barriers, guide rails, attenuating devices,
highway lighting, traffic signals, steel sign structures, signing and
pavement markings, curbing, roadside development items, utility relocation
items, and maintenance and and protection of traffic . |
|